PIERS & HARBOURS - MARINE ASSET MANAGEMENT PLAN

09/03/2023 - PIERS AND HARBOURS - MARINE ASSET MANAGEMENT PLAN

The Harbour Board gave consideration to a report providing a review of the Marine Works Asset Management Plan.Ìý The report included an update on significant and major programmes currently planned and underway within Â鶹Ãâ·Ñ°æ and Bute Council’s Marine Asset Management Plan as well as schemes added since the last update.

 

Decision

 

The Â鶹Ãâ·Ñ°æ and Bute Harbour Board –

 

1.    noted the update on the major programmes currently being addressed within Â鶹Ãâ·Ñ°æ and Bute Council’s Marine Asset Management Plan;

 

2.    noted that £6.5 million worth of capital works are programmed for the financial year 2023/2024; and

 

3.    noted that there was a potential spend of c.£110 million over the next 5 years, the majority of which would support the new CMAL and CFL / CalMac fleet renewal.

(Reference:Ìý Report by Executive Director with responsibility for Roads and Infrastructure Â鶹Ãâ·Ñ°æ dated February 2023, submitted)