Major Projects Update

Meeting: 20/09/2022 - Helensburgh & Lomond Area Committee (Item 9)

9 Helensburgh Waterfront Development (HWD) - Project Position Update pdf icon PDF 209 KB

Report by Executive Director with responsibility for Commercial Â鶹Ãâ·Ñ°æ

:

Additional documents:

Minutes:

Consideration was given to a report which provided a project position update together with confirmation that the Certificate of Practical Completion for Phase 1 of Helensburgh Waterfront Development had been issued with the new Helensburgh Leisure Centre handed over by Heron Bros on Friday 29th July 2022 and fully opened to the public on 3 September 2022.

 

Decision

 

The Helensburgh and Lomond Area Committee:

 

1.    Noted and considered the contents of the Report and

 

2.    Commended the work of the project team and the contractors in delivering the project on time and within budget.